14. (Recommended by Senior Assistant General Manager – Water System and Chief Operating Officer) (Approved by General Manager)
Approval of Amendment No. 1 to the Memorandum of Agreement with the Los Angeles County Flood Control District for implementation of the Tujunga Spreading Grounds Enhancement Project. The Amendment will increase the amount by an additional $23,155,000 and extend the term from July 18, 2019 to December 31, 2023.
In compliance with CEQA Guidelines Sections 15080-15097 and 15164 (Environmental Impact Report previously adopted and Addendum Prepared).