9. RecommendedbyWaterSystem ApprovalofAuthorizationtoReallocateFundsinAgreementNo.47071with Webcor Obayashi Lyles, a Joint Venture, for the Silver Lake Reservoir Complex Storage Replacement Project/Headworks Reservoir Project. The reallocated funds in theAgreement will increase theauthorized expenditure from $75 Million to $85 Million in Phase 3. The Agreement not ot exceed total will remain at $388 Million and will not extend the Agreement duration. The Contract expiration date will remain as December 31, 2025.
DetermineitemisexemptpursuanttoCEQAGuidelinesSection15060(c)(3).