12. Recommended by Power System Ð Engineering, Planning, and Technical Services Approval of Agreement No. 47653 for the Barren Ridge Switching Station to Haskell Canyon Switching Station Transmission Line 1 Upgrade Project with Henkels & McCoy, Inc., for a term of five years and an amount not to exceed $186,603,290, which includes a 30 percent contingency. Determine item is in compliance with CEQA Guidelines Sections 15080-15097 (Environmental Impact Report previously adopted).