19. (Recommended by Senior Assistant General Manager – Water System) (Approved by General Manager and Chief Engineer) Approval of Amendment No. 1 to Contract No. 7520 with Steve P. Rados, Inc., for Construction of the Los Angeles Reservoir Ultraviolet Disinfection Plant. The Amendment will extend the term by one year and increase the contract contingency amount by $2,000,000. Determine item is exempt pursuant to CEQA Guidelines Section 15301.